Installing hot and cold water piping, drainage and booster pumps for a luxury hotel with water-saving fixtures.
About this project
How long did the Hotel Plumbing & Piping Works take?
About 7 weeks on site. We agreed a phased programme with the client up front, so the busiest areas were never without power, water or cooling.
What was the biggest challenge on this project?
Keeping the client operating while we worked. Our engineers surveyed every system first, planned shutdowns out of hours and tested each section before handing it back – the final handover came with test certificates and as-built drawings.